PolicyNov 9, 2026

Norway pauses new grid reservations for data centers

Grid operator Statnett has temporarily stopped taking new connection reservations from data centers, with the pause expected to lift by August 1, 2027 at the latest. About 800 MW of data center load is connected, 4,200 MW is reserved and 9,100 MW is queued, against a national peak demand of just over 25,000 MW.

Why it matters: One of Europe's favorite places to build AI data centers is hitting the limits of its grid, and new technical rules are coming.